STATUS OF MEGA STEEL PLANTS
| Sl. No. |
Company / Project Name |
District |
Location |
Approval Date |
Approved Capacity (MTPA) |
Installed Capacity (MTPA) |
Project Cost (Investment) in CR. |
Investment made so far in CR |
Remarks |
| 1 |
Bhusan Power & Steel Ltd. |
Sambalpur |
Telkai, Lapanga |
15-May-2002 |
15.00 |
3.00 |
55000.00 |
42671.00 |
In Operation, Plant is going for Expansion from 5 MTPArnto 15 MTPA with a Total investment of 55,000 Crore |
| 2 |
Tata Steel BSL Limited (Formerly Bhushan Steel |
Dhenkanal |
Meramandali |
03-Nov-2005 |
6.00 |
6.00 |
20804.00 |
42000.00 |
In Operation |
| 3 |
Arcelor Mittal Nippon Steel India Ltd. |
Jagatsinghpur |
Benefication Plant at Dabuna, Keonjhar and Pellet Plant at Paradeep |
21-Apr-2005 |
6.00 |
6.00 |
10724.00 |
5802.39 |
In Operation, Producting Pellet of 12 MTPA InstalledrnCapacity. The biggest Pellet Complex in India. |
| 4 |
Jindal Steel & Power Limited |
Angul |
Pellet plant at Deojhar,Keonjhar and Steel Plant at Angul |
03-Nov-2005 |
6.00 |
6.00 |
13135.00 |
24744.00 |
In Operation, Plant is going for Expansion of its 6 MTPArnExisting Integrated Steel plant from proposed capacityrnof 18.6 MTPA to 25.20 MTPA with Total Investment ofrn24,652 crore |
| 5 |
TATA Steel Ltd. |
Jajpur |
Duburi, Kalinganagar |
17-Nov-2004 |
8.00 |
3.00 |
47599.00 |
23319.00 |
In Operation, The Plant is going for Expansion of itsrnCrude Steel Production from 3 MTPA to 8 MTPA with arnTotal Investment of 47,599 Crore. |
| 6 |
Rungta Mines Ltd. |
Dhenkanal and Keonjhar |
Jharabandha and Karakehendra |
03-Nov-2005 |
10.55 |
0.50 |
18921.00 |
713.00 |
Plant is going for Expansion of its Intregrated SteelrnPlant from Proposed capacity of 2.85 MTPA to 7.55rnMTPA at Dhenkanal and from 0.53 MTPA to 3 MTPA atrnKeonjhar with total investment of 18,921 Crore. Whilernthe other Steel Plants of the Company atrnKamandha(0.35 mtpa), Sundargarh andrnKarakhendra(0.15 mtpa), Keonjhar are already inrnOperation |
| 7 |
Shyam Metalicks and Energy Ltd. |
Sambalpur |
Pandloi, Rengali |
09-Feb-2004 |
2.10 |
0.50 |
2075.00 |
1107.00 |
In Operation, SMS-1.6, DRI-0.55, Blast Furnace-0.39rnMTPA, Pellet 1.8 MTPA, Rolling Mill-0.9 MTPA, SinterrnPlant-1.3 MTPA |
| 8 |
Jindal Stainless Ltd. |
Jajpur |
KalingaNagar |
09-Jun-2005 |
3.10 |
1.10 |
23625.00 |
9923.00 |
In Operation, Crude Stainless-2.1 MTPA, Rolling Mill-1.6rnMTPA. |
| 9 |
Jindal Steel Odisha Ltd |
Angul |
|
15-Dec-2021 |
19.20 |
0.00 |
97070.00 |
0.00 |
The total investment includes the investment for a 12.5rnMTPA cement plant |
| 10 |
JSW Utkal Steel Ltd |
Jagatsingpur |
Godkujang, Nuagaon, Dhinkia |
02-Jun-2017 |
12.00 |
0.00 |
50000.00 |
0.00 |
At Project Stage. 12 MTPA Steel with 32 MTPA PelletrnPlant |
| 11 |
Arcelor Mittal Nippon Steel India Ltd. |
Kenderapada |
Mahakalapada |
17-Dec-2021 |
24.00 |
0.00 |
102275.00 |
0.00 |
Approved by State Govt. |
| TOTAL |
111.95 |
26.10 |
441228.00 |
150279.39 |